Hammerfest LNG plant delayed
2009-11-23
Technical challenges have delayed the
The Snøhvit facilities at Melkøya have been shut down this autumn for planned upgrading and maintenance.
All replaced and upgraded parts of the cooling plant were started up and appeared to function. But two technical challenges have arisen during this phase.
The first was a fault in one of the plant’s utility systems, which has now been repaired.
Arising later in the
It has now been decided that this motor must be replaced by a reserve unit which is stored at the nearby Polarbase in Hammerfest.
Replacement work is already well under way, and personnel from the operations organisation and the contractor will work around the clock until the plant is ready to resume
The unexpected faults which have occurred during the first
Source: press release